Highway 27 Vicinity
  • Expect borehole drilling on the south side of Humber College Blvd. at Highway 27.
  • Activities to remove four median in the area continues. Most of the work occurs at night.
Highway 400 Bridge Rehabilitation
  • Large flat beds continue to deliver prefabricated steel girders to the laydown areas beside the highway.
  • Using heavy equipment, the girders are raised and placed on the scaffolding, as part of the process that will be used to build the bridge decks beside the highway and out of the way of traffic.
Maintenance and Storage Facility (MSF)
  • Foundation work at the MSF site progresses.
Roadworks on Finch Avenue West
  • Road widening on the north side of Finch Ave. W., between Keele St. and Romfield Ln., continues and includes excavation, asphalt removal, as well as placing and compacting granular.
  • Please drive safely and watch for workers in the area.
  • Installation of temporary traffic signals is underway at Tangiers Rd.